Building regulations: full plans or building notice?

The two routes to building regulations approval for an extension, loft or basement, how they differ in risk, and why we use full plans on most projects.

Published

Every extension, loft conversion, basement and conversion needs building regulations approval, whether or not it needs planning permission. With council building control there are two routes: a full plans application or a building notice. On almost every project we run, we use full plans.

Full plans

Detailed drawings and a specification are submitted before work starts. Building control checks them against the regulations and issues an approval, usually with conditions. An inspector then visits at key stages of construction.

Why we prefer it:

  • Problems are resolved on paper, not after they are built.
  • Contractors price from approved drawings, so tenders are comparable and cost is more certain.
  • The contractor knows exactly what is required, which reduces argument on site.

The council must decide a full plans application within five weeks, or two months if the applicant agrees to an extension.

Building notice

Notice is given at least two working days before work starts, with minimal information. There is no plan approval: compliance is checked only by inspection on site.

Where it can work: small, simple jobs with standard details and an experienced builder. It cannot be used for buildings covered by the fire safety order, such as shops and offices, or for work close to or over certain sewers.

The risk: if the inspector disagrees with something already built, it has to be altered at the owner's cost. On a substantial house, that risk outweighs the time saved.

Council or registered approver

Building control can be provided by the local authority or by a registered building control approver, a private company registered with the Building Safety Regulator. The local authority issues a completion certificate at the end of the work; a registered approver issues a final certificate.

Keep the certificate

Buyers' solicitors will ask for it on sale. Without it, a sale can be delayed while retrospective approval is sought.

Our building regulations drawings service prepares full plans packages coordinated with the structural engineer's design.

Begin a conversation

Tell us a little about the house or site and we'll arrange a first conversation with a director. Or call us on +44 (0) 20 800 444 644.

  • Every enquiry is treated in confidence.
  • For sensitive settings, we'll outline the likely planning considerations at the first meeting.
  • Structure and planning reports are coordinated in-house with our sister practices.

I'm