How long does planning permission take in London?

Realistic timescales for householder, prior approval, lawful development and larger applications in London, and what most often causes delay.

Published

For a typical London house extension, allow around three months from submission to decision. The statutory target for a householder application is 8 weeks, but the clock starts only when the council has validated the application, and validation alone can take one to three weeks in a busy borough.

Typical timescales by application type

Application Target from validation What to allow in practice
Householder planning application 8 weeks 10 to 14 weeks
Larger home extension prior approval 42 days (fixed) 7 to 9 weeks
Lawful development certificate No statutory period, usually 8 weeks 8 to 10 weeks
Listed building consent 8 weeks 10 to 16 weeks
Minor application (for example a conversion to flats or a small new-build) 8 weeks 3 to 5 months
Major application (10 or more homes) 13 weeks 6 months or more, plus the legal agreement

Councils can ask to extend the period by agreement. Most do on larger schemes, and refusing usually leads to a refusal rather than a quicker approval.

What causes delay

  • Invalid applications. Missing drawings, the wrong ownership certificate or a missing supporting report stop the clock before it starts. Each council publishes a local validation list; we check it before submitting.
  • Supporting reports. Flood risk, trees, heritage, daylight and parking reports are often required, and are quickest when commissioned at the start. Green Code Consultants can show which reports a council is likely to ask for.
  • Amendments. If the officer asks for changes late in the process, the council may re-consult neighbours, adding two to three weeks.
  • Committee. Applications with many objections, or called in by a councillor, go to a planning committee, which can add a month or more.

After the decision

A planning permission normally lasts three years. Conditions, such as approval of materials, may need to be discharged before work starts, and each discharge application has its own 8-week target. If permission is refused, a householder appeal goes to the Planning Inspectorate and currently takes several months. Our fixed fee includes a free revised resubmission if planning is refused.

Building regulations approval and party wall notices can run in parallel with planning, so the start on site need not wait for each step in turn.

Begin a conversation

Tell us a little about the house or site and we'll arrange a first conversation with a director. Or call us on 020 8004 4464.

  • Every enquiry is treated in confidence.
  • For sensitive settings, we'll outline the likely planning considerations at the first meeting.
  • A director replies personally. The first conversation covers your site, your brief, the likely planning route and how an appointment would work.
  • Structural engineering, specialist planning reports and construction can be coordinated through the group with our sister companies, if you want them.
I'm